1th Risk Management Plan

Project Name:   2D Animation
Class:          41328-3B
Name:         Ho Kim Pong
Risk No
Risk Event
Probability
Impact
Mitigation
Contingency
1
Team members are not familiar to the “Adobe Premiere”.
High
Medium
-Learn the software together before the project start. -Prepare more time in the post-production phase
-Ask professional for help -Hire vendor to perform the task
2
Team Members are sick
High
Medium
-prepare more time for different tasks
-Revise the schedule
3
Equipment damaged
Medium
High
-Use the equipment carefully.
-More than one team members are responsible on the equipment.