2010年11月27日

6th Committee Meeting

Institute of Vocational Education
(Sha Tin Campus)
PROJECT NAME
6th Committee Meeting
Date: 23 th Nov 2010(Tuesday)
Time: 12:30pm – 1:30pm
Venue: Library, 21 Yuen Wo Road, Sha Tin, Hong Kong.
Present: Ho Kim Pong, Wong Pak Sze, Wong_Siu Fung
Absent: None
AGENDA
1.      Confirmation of minutes of last meeting
        -  Content of story refine
        -  Others role design
        -  Problems of delayed

2. Progress report from
2.1. Wong Pak Sze
-  Drawing Main role movement
2.2. Wong_Siu Fung
- Other role design
- Color makeup and testing
2.3. Ho Kim Pong
- Drawing the scene
- Prepare the agenda for the meeting.
- Prepare PowerPoint of presentation.
.
3. General discussion
3.1. Project Schedule
-   Continuous discuss storyboard of camera angle.
3.2. Task Allocation
-   Ho Kim pong pass the movement of character Wong Pak Sze
4. Any other business
-   Update the Blogger
-   Learn how to using Graphics tablet
5. Date, Time & Place of next Meeting
-   7 th Dec 2010
6. Adjournment
-   1 ~ 2 hours
Prepared by:
Ho Kim Pong
23 th Nov 2010

2010年11月26日

2rd Risk Management Plan


Project Name:   2D Animation
Class:                41328-3B
Name:                Ho Kim Pong
 
Risk No
Risk Event
Probability
Impact
Mitigation
Contingency
1
Team Member work does not match that their style, track is different.
High
High
- Prepare a detail document and guideline that everyone sees this document.
-Analyze team Member work and use to other way.
2
Team Member has a wrong perspective drawing
High
High
- Learning a accuracy perspective drawing form lecturer.
-Use the 3D Layer try to make it like a perspective drawing